The UK Government has promised to eliminate coal-fired thermal generation from the UK grid by October 2024. The three remaining units, all part of the Ratcliffe-on-Soar power station are scheduled to shut down in September 2024.

Will this be completed as scheduled?

Resolves as YES on 2024-10-01 if closure of all coal units is confirmed. Confirmation could be by press release, physical destruction or other convincing evidence (e.g. deregistration as Balancing Mechanism units).

Get
Ṁ1,000
and
S3.00
Sort by:

@traders The Balancing Mechanism Units have notified their shutdown (link is to RATS-4, the last to turn off). They will not generate any more power today.

Uniper, the operator of the power plant has released a press release saying that the plant will shutdown permanently at "midnight" today.

Accordingly, I will resolve YES tomorrow unless everyone has a last minute change of heart and they reverse the above.

The closure of the final coal plant in the UK, Ratcliffe-on-Soar, at midnight on 30th September 2024, marks the beginning of a new era.

How will we know whether it is 1 second before or 1 second after?

The Guardian reporting today is the final day.

Still burning coal today! Two days left to use up the remaining coal and announce the shutdown.